SAISD Bond 2026: What The $600 Million Ballot Measure Would Pay For

After Questions Over Bond 2020, SAISD Is Asking Voters To Look At What Comes Next — From Aging School Systems And Security To Technology And Career Readiness

San Antonio ISD voters will decide Nov. 3 whether to approve another $600 million in bond funding, six years after voters approved the district’s $1.3 billion Bond 2020 program.

About $420 million from that earlier bond remains as projects continue, while SAISD is also pursuing a targeted forensic examination amid questions about spending and management, particularly some East Side projects.

The question now is what another $600 million would actually fund. Rather than building a collection of new schools, SAISD says the proposal would support “school modernization, capital system replacements, and safety and security upgrades,” including aging systems, classroom improvements and technology across campuses that have been operating for decades.

In that sense, much of the package functions as a maintenance and sustainability investment, helping SAISD keep existing schools functional while larger renovations and rebuilding projects continue elsewhere.

The bond is split into three propositions totaling $600 million, while a fourth, separate Voter Approval Tax Rate Election would provide operating money for programs, employees and student initiatives.

What Is On The November Ballot?

SAISD trustees voted in August to place four propositions before voters. Three make up the district’s proposed $600 million bond package, while a separate Voter Approval Tax Rate Election, or VATRE, would provide additional operating revenue.

Proposition A is the VATRE. It would increase the district’s Maintenance and Operations tax rate by 3.17 cents and is expected to generate about $5.5 million in additional revenue. SAISD says the money would support college and career readiness, teacher pipeline programs and compensation initiatives.

The actual bond package is divided among three other propositions:

Proposition B — $492 million: School modernization, major building-system replacements and safety and security improvements. Projects could include classroom renovations, replacement of chillers and boilers, plumbing, roofs and windows, new buses with three-point seat belts, police vehicles, security fencing, lighting, vestibules, fire alarms and ADA improvements.

Proposition C — $102 million: Technology improvements, including network infrastructure and devices used for teaching and learning.

Proposition D — $6 million: Improvements to Alamo Stadium and the Convocation Center.

SAISD Bond VATRE 2026. San Antonio Independent School District
SAISD Bond VATRE 2026. San Antonio Independent School District

The district says all four propositions would initially cost the average SAISD homeowner about $1.99 more per month in 2026. The estimated monthly increase would rise to $3.25 in 2027 and eventually reach $5.76 by 2030. Qualifying homeowners with an over-65 exemption would not see their property taxes affected by the proposals under the conditions outlined by the district.

Which Schools Would Get The $492 Million?

Unlike traditional school bond elections in which districts identify campuses and projects before voters go to the polls, SAISD does not plan to provide a final campus-by-campus project list for most of Proposition B.

District spokesperson Laura Short said SAISD believes decisions should be based on current conditions when bond money becomes available rather than committing years in advance to projects based on projections that could change.

“SAISD believes the most responsible approach is to make certain future bond decisions are made using real-time data and identified needs when funds become available, rather than relying solely on long-term projections,” Short said.

The district points to changing enrollment, facility conditions and community needs as reasons for maintaining flexibility.

That approach is significant for a district already undergoing major changes to its footprint. SAISD has closed schools as enrollment has declined and officials expect additional changes in the coming years. That creates the possibility that a campus considered a priority today could have a different future by the time later bond dollars become available.

SAISD’s Blue Ribbon Task Force assessed campuses and identified facility conditions and needs, and an earlier snapshot identifies campuses needing safety, security and facility upgrades. But individual projects would still require future approval.

Bond 2020 Still Hangs Over The New Request

The unanswered questions surrounding the new bond are amplified by what is happening with the old one.

Voters approved $1.3 billion in 2020 for major renovations at dozens of campuses along with HVAC, security and technology improvements. Roughly $420 million remains unspent as of this fall. Inflation and rising construction costs have forced SAISD to reconsider or modify projects, while school closures have also affected where some previously approved bond dollars will ultimately go.

The district is now seeking an independent accounting firm for a targeted forensic examination of the 2020 bond program. A forensic examination does not itself mean wrongdoing occurred, but it can provide a more detailed review of expenditures, financial records and the management of bond money.

Related: SAISD Wants Another $600 Million As $420 Million Remains Unspent And East Side School Projects Stall

SAISD has also launched its Bond 2020 Explorer, an online dashboard allowing residents to examine bond work by campus and filter information including enrollment, facility conditions, enrollment projections and previous bond investments.

The remaining money is particularly relevant on the East Side, where questions have persisted over projects at campuses including Martin Luther King Academy and S.J. Davis Middle School. Trustees recently delayed additional Bond 2020 spending involving those campuses amid broader questions about allocations from the remaining funds.

Voters Will Decide Nov. 3

In regards to the 2020 bond, voters are entitled to know why so much money remains unspent, what the forensic examination finds and whether projects promised to communities, particularly on the East Side, will be completed as expected.

But over the next few weeks, the question before voters is also about the schools that are not currently under major construction.

SAISD argues that avoiding a rigid project list gives the district flexibility it did not have when conditions changed after voters approved Bond 2020.

The November vote will ultimately ask whether SAISD should receive additional funding to maintain and modernize the campuses that must continue serving students while larger bond projects move forward elsewhere in the district.

Early voting runs Oct. 19 through Oct. 30. Election Day is Nov. 3. For information about SAISD’s Vatre 2026 Bond visit, saisd.net/bond2026.

Subscribe to Our FREE Weekly Digital Issue

* indicates required

Related Articles

Jefferson Bank

Latest Articles